2 min read

How long does a basement take?

The short answer

Allow 12 to 18 months from first drawings to moving back down: around six for design and approvals, then 30 to 40 weeks on site. The digging is the quick part.

Basement family room opening onto a planted lightwell

A basement under a London terrace is the biggest job we do, and the one with the most waiting in it. The digging is quick. Everything around it isn’t.

Before anyone picks up a shovel

StageTypical time
Survey, design and structural engineering6–10 weeks
Planning, which most councils require for basements8–13 weeks
Party wall notices and awards, alongside planning2–3 months
Thames Water build-over agreement, if drains are affected4–8 weeks
Several of these run at the same time. Six months from first drawings to start on site is typical.

On site, stage by stage

  1. Weeks 1–3. Hoarding, a conveyor out to the skip, and temporary props.
  2. Weeks 4–14. Underpinning the walls in short sections and digging out between them.
  3. Weeks 15–20. The new slab, then the waterproofing: a drained membrane and twin pumps.
  4. Weeks 21–30. Lightwells, structure above, drainage and services.
  5. Weeks 31–38. Plaster, floors, joinery and handover.

Why it’s never the digging

Underpinning goes in one bay at a time, in a set order, and each bay has to cure before its neighbour can be dug. The waterproofing is tested before it’s covered. Building control and the party wall surveyors inspect at agreed stages. None of that can be rushed, and none of it should be.

Can you stay in the house?

Usually not for the middle four to six months, while the ground floor is propped and open. Most clients rent nearby and move back for the finishes. We plan the programme around the move, not the other way round.

Keep reading

All the answers